What is required if there is a deviation from the lift plan?

Prepare for the NCCCO Advanced Rigger Test with comprehensive flashcards and multiple-choice questions. Each question is accompanied by hints and detailed explanations to ensure deep understanding. Master the concepts and clear your certification exam!

When there is a deviation from the lift plan, creating a new lift plan is the correct response to ensure safety and compliance with established protocols. A lift plan serves as a comprehensive guide that details the specifics of the rigging operation, including equipment, loads, locations, and methods. Any change to the initial plan can introduce unforeseen risks or complications, and a new lift plan facilitates a thorough reassessment of the situation.

This new plan should include updated information that reflects the altered scope of the lift, including any changes to load weights, rigging configurations, and site conditions. It provides all team members with clear and current instructions on how to proceed safely, ensuring that the lift operation continues to comply with safety standards and regulations.

While the supervisor or rigger's permission might be part of the process in certain contexts, relying solely on verbal permission without an updated plan does not address safety comprehensively. Similarly, mark-ups on the existing lift plan can lead to confusion and misinterpretation, lacking the clarity needed for safe operation. Therefore, generating a new lift plan is the most effective way to manage any deviations from the original plan.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy